Transformer is to be unpacked fully and made to stand vertical before carrying out any site tests including measurement of IR value by megger. Store the transformer vertically.
Before energizing, one terminal of all the secondary windings not being used is to be grounded.
Primary connection is to be tightened sufficiently to avoid hot connection.